Hi Frédéric,
this is a shortcoming in current implementation due to the fact that
can not choose which resources should go into the PB.project. There are
two ways to handle this. Disable the rapid turnaround mode or add the
resources manually to the PB.project.
Ulrich
Am Donnerstag, 17.04.03 um 15:29 Uhr schrieb Frédéric Dreier:
> Hi,
>
> I used to access resources (with ProjectBuilder) using :
>
> resourceManager().bytesForResourceNamed("lala.plist",null,null)
>
> For some reason, i cannot get it working with wolips
> (nullpointerexception).
> Should i add some path or copy files somewhere? Actually resources are
> in
> the project root and are also in the builded jar file.
>
>
> Thx,
>
> dreier
>
>
This archive was generated by hypermail 2.0.0 : Thu Apr 17 2003 - 10:44:37 EDT